Issue - decisions

Controlled Parking Zones - Update and Funding

22/05/2019 - Controlled Parking Zone Programme - Update and Funding

Cabinet resolved to:

 

(i)  Agree the roll-out of the Controlled Parking Zone project at an estimated total cost of £3.523m as detailed in the report, to be funded initially by borrowing and on the basis that the funding, plus interest costs, shall be recovered by the income raised from the project in the initial years;

 

(ii)  Agree the carry forward of the remaining capital allocation of £260,000 from 2018/19 to the 2019/20 Capital Programme and the reprofiling of the current allocation (totalling £860,000) to 2019/20;

 

(iii)  Agree additional capital funding of £901,600 for 2019/20 and £1,761,600 for 2020/21;

 

(iv)  Delegate authority to the Director of Law and Governance, in consultation with the Cabinet Member for Enforcement and Community Safety and the Cabinet Member for Regeneration and Social Housing, to amend the Council’s Domestic Vehicle Footway Crossover Policy based on the principles set out in section 2.4 of the report, to ensure consistency with the new CPZ arrangements; and

 

(v)  Agree to rescind the scoring matrix element of the decision-making criteria approved by the Cabinet under Minute 25 (18 September 2018), to be replaced by the arrangements detailed in paragraph 2.5.4 of the report.