Procurement Plan and Commissioning Intentions 2015/16

Decision Maker: Health & Wellbeing Board and ICB Sub-Committee (Committees in Common)

Decision status: Approved

Is Key decision?: No

Is subject to call in?: No

Purpose:

Under the Council’s Contract Rules (Rule 25) there a requirement to report the Procurement Plan for all new contracts (including extensions, additions and renewals) with a Contract Value of £500,00 or above scheduled to start in the next financial year, which are funded in part or in whole from the Public Health Grant or from within social care budgets.

 

The Board will be presented with Procurement Plan and be asked to agree the proposed Plan in its entirety or identify any individual procurements / contracts which the Board requires separate more detailed Procurement Strategy Reports to be submitted to it for closer consideration.

Decision:

Having received the report and discussed the priorities, the Board:

 

(i)  Agreed the strategic framework for commissioning health and wellbeing programmes for 2015/16, as set out in the report

 

(ii)  Noted the list of contracts over £500,000 that were due to expire during the financial year, as identified in section 7 and Appendix A of the report.

 

(iii)  Noted that the next stage was to look at resourced delivery programmes, in respect of what was being done now, what could be stopped or done differently, and what else was needed to make a difference.

Report author: Matthew Cole

Publication date: 19/03/2015

Date of decision: 17/03/2015

Decided at meeting: 17/03/2015 - Health & Wellbeing Board and ICB Sub-Committee (Committees in Common)