Decision details

Establishment of a Council-owned Energy Services Company

Decision Maker: Cabinet

Decision status: Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

The Cabinet will be asked to approve proposals for the establishment of an Energy Services Company to install energy technologies and establish energy savings.

Decision:

Cabinet resolved to:

 

(i)  Approve the principle to establish an Energy Services Company (ESCO) specifically for the purposes of producing and supplying renewable energy, energy efficiency and related services to schools, the corporate estate, housing and the community subject to detailed business planning and due diligence;

 

(ii)  Approve the interim mission and objectives of the ESCO to frame detailed business planning as follows:

 

a)  The mission of the ESCO is to help deliver the Council’s energy and carbon reduction objectives;

 

b)  The proposed objectives of the ESCO will be to:

 

·  generate savings and surpluses;

·  create and deliver energy related benefits for the corporate estate, housing and schools;

·  identify and deliver affordable energy projects;

·  reduce fuel poverty;

·  reduce carbon emissions;

·  create wider social and economic benefits for the community;

·  develop local energy expertise to support local economic development.

 

(iii)  Note that a further report would be submitted to Cabinet later in the year setting out a detailed business case prior to the establishment of the ESCO;

 

(iv)  Approve the allocation of £250,000 from the Invest to Save budget to fund detailed investment programme feasibility studies, business planning and financial and legal advice as set out within the report;

 

(v)  Approve, subject to satisfactory detailed feasibility studies and availability of satisfactory funding, the procurement of the following investment projects for direct delivery by the Council and potentially through an ESCO, as detailed in paragraph 2.2.3 of the report:

 

a)  Street lights LED replacement programme (borough-wide);

b)  Photovoltaic (PV) enabled street columns programme (borough-wide);

c)  Wind turbines programme (subject to Cabinet’s agreement to the locations);

d)  River Roding water turbine scheme;

e)  Barking Town Hall renewable energy and energy efficiency works;

f)  Gascoigne renewable energy and combined heat and power facility;

g)  Photovoltaic panel energy programme (corporate estate and initial HRA dwellings);

h)  Combined Heat and Power programme and associated energy efficiency works to Housing Revenue Account properties subject to HRA financing restrictions;

i)  Children’s centres photovoltaic panel programme;

j)  Heat, power and energy services to the borough’s schools.

Report author: Jonathan Bunt

Publication date: 26/03/2015

Date of decision: 24/03/2015

Decided at meeting: 24/03/2015 - Cabinet

Effective from: 03/04/2015

Accompanying Documents: