The Council’s
DMP, the Managing Director for BD Management Services and BD
Service Delivery (MDBDM) and the Assistant Construction Director
(ACD) for Be First delivered a presentation into how they worked
with residents affected by Capital Works.
The Chair questioned
why resident satisfaction surveys completed following works were
being returned to the contractors rather than to officers within Be
First, as this may put residents off from lodging any issues. The
ACD stated that this would be amended going forward as a result,
with surveys either being returned to Be First or having an option
to be sent back to Be First. The MDBDM stated that BD Services had
their own Resident Liaison Officer (RLO) who carried out
satisfaction surveys with the customer, who was independent from
the contractor and any staff who were delivering the work. My Place
also carried out their own spot checks and as such, did not just
take the word of BD Services on feedback, adding a further level of
scrutiny to the satisfaction results.
In response to a
question, the DMP stated that they would share a clear
ward-by-ward/block-by-block understandable explanation of what the
Capital Works programme was with the Committee as soon as possible.
Members also noted that whilst Be First was fairly good at sending
Ward Members any letters that were due to be sent out to the local
community regarding capital works, that sometimes Members received
these with too short notice to amend these if necessary.
In response to several
questions, the ACD stated that:
- Mistakes had been
made historically but that both himself and other colleagues were
actively working to improve capital works programmes;
- In relation to the
recording of quality, the ACD had been asked to increase the level
of Clerks of Works. He had one clerk of works out at the moment,
with another two scheduled to join and that collectively they would
be leading on the clerk of works process and providing feedback.
The ACD’s team would also be going out to speak to residents,
ensuring that they were happy with any work carried out and
providing feedback;
- He had been given the
lead for looking at all of the Be First Freedom of Information
requests and complaints, so that he would be able to see these
first hand and cross-reference these against the data that the
contractors had been supplying;
- All Section 20 works
went through a Section 20 framework. This was a historic framework
that was due to end between April and May 2021. The team went out
and priced quality and it was currently the case that contracts
were awarded on a price-quality basis. Whilst historically, the
Council was led by price, it was now the case that the winning
contractor would not necessarily be providing the cheapest option
as this would need to be weighed against the quality required. Once
the winning contractor was awarded the contract, the figures that
would come through for any capital works to be undertaken would be
assessed by a Quantity Surveyor (QS). Be First had an external QS
who would analyse the prices presented and would agree or disagree
to these offering the best value. There would also be a secondary
check from the Be First team, as well as a QS historically from the
Council. The prices would therefore go through three rounds of
checks before they were finalised and charged to the
resident;
- In relation to the
external work team, there was a project manager who adhered to the
day-to-day running of the project, a clerk of works, a portfolio
lead who oversaw the team, an appointed contract administrator and
a QS. The contract was being monitored at project level by the
project manager, the portfolio lead, the QS and the contract
administrator. These four individuals would also hold daily
conversations with My Place and the contractor, discussing the
contract and its contents. The clerk of works would attend the site
two or three times a week;
- He held weekly
meetings with his portfolio leads to ascertain progress and
performance and hear more about meetings that had been held with My
Place colleagues and contractors. His team did a cash flow
forecast, where they dealt with the QS and the QS’s
expenditure from the contractor would be recorded. The ACD also had
meetings with BDMS to discuss strategies and share information;
and
- If a contractor fell
short of delivery, the ACD would discuss this with the Managing
Director of that contractor within a week and they would have
meetings on site.