Preparing for Building Schools for the Future

05/08/2005 - Preparing for Building Schools for the Future

Received a report setting out the latest position regarding Building Schools for the Future following a meeting with officials from the Department for Education and Skills (DfES) who have indicated that Barking and Dagenham will be in the next waves of the Building Schools for the Future programme.

 

Agreed, in order to rebuild, refurbish and / or remodel secondary schools in the Borough, to:

 

  1. A sum of £700,000 to be added to the Capital Programme, as set out in paragraph 4.4 of the report, to allow some early work in drafting proposals, research on site difficulties and drawing up feasibility options for the development of school rebuilding and / or refurbishment of the secondary school estate.  This will include the establishment of a Local Education Partnership, legal and financial fees for advice (subject to undergoing the Capital Programme Monitoring Office process);

 

  1. The sum of £700,000 to be initially funded from slippage from the Warren Comprehensive School Science Facility scheme;

 

  1. Note that future bids for resources will be considered in February 2006, as set out in paragraph 4.3 of the report;

 

  1. The advancement of the Building Schools for the Future process along the lines set out in the report and subject to consultation with the DfES / Partnership for Schools; and

 

  1. Authorise the Director of Education, Arts and Libraries to enter into the process of securing advisors to help develop the process.