11/09/2009 - Highways Investment- Accelerated Programme

Received a report from the Corporate Director of Customer Services concerning proposals to accelerate the Highways Investment Programme of work to three years rather than the previously agreed four years with £2m of extra investment.

 

Agreed, in order to assist the Council to achieve its Community Priorities of ‘Clean’ and ‘Prosperous’, that:

 

(i)  the Highways Investment Programme is shortened to three years with the capital allocation for 2009/10 increased to £10 million, and the allocation for 2010/11 increased to £3.5 million; and 

 

(ii)  £1million of additional investment is made in 2009/10 and a further £1million in 2010/11; found through prudential borrowing supported by reduced spend on emergency highways repairs. 

 

The Executive expressed its pleasure with the work carried out to date.